- Home
- Township Government
- Departments
- Public Works
- Engineering
- Construction / Improvement Projects
- Peterson Road Street Improvements
Peterson Road Street Improvements
Overview
Peterson Road is the last remaining Township maintained gravel road. Gravel road maintenance is different than pavement maintenance and requires special maintenance efforts. Erosion of the gravel surface occurs occasionally and must be reviewed after larger storms. Gravel is added to maintain a suitable driving surface.
Lot development of Three Oaks and the Mehegan Lane connection were built in 2018. Homes are currently being constructed within the Three Oaks development. As construction has been underway, the road connection has been closed. As the development project nears full buildout, the roadway will be opened and more traffic will use Peterson Road south of Mehegan Lane. Opening Mehegan lane to Peterson Road will be a change for the current residents who reside on Peterson Road as it will increase Peterson Road vehicle usage.
On December 12, 2019, the White Bear Township Town Board ordered the preparation of a feasibility report for Peterson Road street improvements.
Improvements:
- Watermain extension
- Sanitary sewer extension
- Stormwater collection and treatment
- Bituminous surfacing
- Concrete curb and gutter
- Driveway aprons
- Pedestrian improvements
- Drainage improvements
Project Updates:
April 16, 2021 - XcelEnergy gas is completing the new main line work and will begin connecting homes to the new gas line.
April 12, 2021 - Private utility relocations along Peterson Road will begin tomorrow, April 13th.
April 6, 2021 - Tree and brush clearing has been completed. Contractor will continue removing the cut down trees and grind out the stumps today.
April 2, 2021 @ 1:00 pm - The tree and brush removal equipment will start to be delivered today and possibly Saturday. Tree and brush removals will be begin Monday morning.
April 1, 2021 - Tree removals have been marked with ribbon. Tomorrow brush limits will be marked.
March 30, 2021 @ 4:00 pm - A pre-construction meeting was held today to discuss the project with the contractor and private utilities. We will be contacting each resident to discuss the project with them. We will discuss the water main and sanitary sewer service locations, tree/brush removals and any address questions.
March 30, 2021 - A pre-construction meeting occurred this morning. Currently the contractor is placing tree removal markings on affected trees.
March 2, 2021 - The contractor is moving equipment in today due to upcoming spring road restrictions starting. No work will be done at this time. We will provide updates before the contractor begins any construction activity.
November 3, 2020 @ 4:15 pm - Private utility companies are marking the locations.
November 2, 2020 @ 3:45 pm - Private utility companies are marking their locations.
October 30, 2020 @ 2:15 pm - Preliminary staking of the new structures will begin for design review by the contractor.
Preliminary Project Schedule
Authorize Preparation of Feasibility Report December 12, 2019
Town Board Discussions Various Meetings
Accept Feasibility Report June 1, 2020
Call for Public Hearing
Neighborhood Informational Meeting June 17, 2020
Public Hearing July 6, 2020
Open House August 5, 2020
Accept Plans and Specifications August 17, 2020
Authorize Advertisement for Bids August 17, 2020
Bid Openings September 16, 2020
Award Contract September 22, 2020
Begin Construction
Substantial Construction Completion
Authorize Amount to be Assessed
Assessment Hearing / Adopt Assessments
Construction Completion
-
Larry Poppler
Town Engineer, TKDAPhone: 651-292-4457